Additional information:
As previously described, I started five jobs scheduled fifteen minutes
in advance. The first two were started from BAT, after which BAT became
unable to connect and no new consoles could be started. I then
scheduled three more from an already-open console, for a total of five
jobs, four with PRI=10 for 10:00:00, one with PRI=15 for 11:00:00.
At this time, three of the scheduled jobs (the first, second and fourth
scheduled) have completed, the third is still running, and the fifth
(PRI=15) is waiting on completion of the third before it can run. I am
now once again able to start new consoles (I started seven new consoles
at once with no problem) and run BAT without problems. I have not tried
to start any additional jobs at this time.
I don't, unfortunately, know the minimum number of jobs that had to
complete before I could begin opening new console connections again.
--
Phil Stracchino, CDK#2 DoD#299792458 ICBM: 43.5607, -71.355
alaric AT caerllewys DOT net alaric AT metrocast DOT net phil AT
co.ordinate DOT org
Renaissance Man, Unix ronin, Perl hacker, SQL wrangler, Free Stater
It's not the years, it's the mileage.
------------------------------------------------------------------------------
Virtualization & Cloud Management Using Capacity Planning
Cloud computing makes use of virtualization - but cloud computing
also focuses on allowing computing to be delivered as a service.
http://www.accelacomm.com/jaw/sfnl/114/51521223/
_______________________________________________
Bacula-users mailing list
Bacula-users AT lists.sourceforge DOT net
https://lists.sourceforge.net/lists/listinfo/bacula-users
|