tuning dumpcycle, runspercycle, and tapecycle
2005-02-13 12:13:36
Greetings. For backups to a server with one DLT-IV drive, I would like to
change the tape once per week. During the week, I would like to do one
full backup on day 1, and incremental backups on days 2-5.
To do this, I set "dumpcycle 1 week" and "runspercycle 5" and "tapecycle 1
tapes". However, in the dump reports, I get this message every dump, even
on the incremental days:
planner: tapecycle (1) <= runspercycle (5)
planner: Full dump of hostname.networktest.com:/ promoted from 6 days
ahead.
This sounds like amanda does a full dump each time. True?
If so, what is the correct config for one full dump plus four incremental
dumps?
This is for 2.4.4p4_2 on FreeBSD 4.10.
Thanks!
dn
|
<Prev in Thread] |
Current Thread |
[Next in Thread>
|
- tuning dumpcycle, runspercycle, and tapecycle,
David Newman <=
- Re: tuning dumpcycle, runspercycle, and tapecycle, Gene Heskett
- Re: tuning dumpcycle, runspercycle, and tapecycle, David Newman
- Re: tuning dumpcycle, runspercycle, and tapecycle, Jon LaBadie
- Re: tuning dumpcycle, runspercycle, and tapecycle, Gene Heskett
- Re: tuning dumpcycle, runspercycle, and tapecycle, Steve Wray
- Re: tuning dumpcycle, runspercycle, and tapecycle, Gene Heskett
|
|
|