Hi,
We are planning to Upgrade TSM server from 6.3 to 7.1.
Proposed methodology
1. Install 6.3 in New AIX Box
2. Backup and restore DB backup to new server
3. Test backup and restore activity with version 6.3 in New server.
4. Then upgrade 7.1.
For testing backup and restore, we want to create new logical library and assign a drive to new Server.
We would like to do this after installing TSM 6.3
Library Stats
90 Storage Slots
6 Drives
6 I/O Slots
Our agenda is assign 2 storage slots and 1 drive to new server for testing purpose. After that we plan to delete the logical library assign back resources to existing logical library.
Kindly suggest a "Best Practice" for creating a logical library.
Regards,
Mohan
We are planning to Upgrade TSM server from 6.3 to 7.1.
Proposed methodology
1. Install 6.3 in New AIX Box
2. Backup and restore DB backup to new server
3. Test backup and restore activity with version 6.3 in New server.
4. Then upgrade 7.1.
For testing backup and restore, we want to create new logical library and assign a drive to new Server.
We would like to do this after installing TSM 6.3
Library Stats
90 Storage Slots
6 Drives
6 I/O Slots
Our agenda is assign 2 storage slots and 1 drive to new server for testing purpose. After that we plan to delete the logical library assign back resources to existing logical library.
Kindly suggest a "Best Practice" for creating a logical library.