Thanks Bryan,

 

It happens directly after reboot.. 

 

The thing is:

-          I have deactivated all polices

-          Stop our media server

-          And then restarted netbackup on the master.

 

So there are absolutely no action going on (no backup, no user backup, no
restore, no staging) only internal netbackup work
.

At once when netbackup on the master gets active, it starts bpdbm process
after bpdbm process. It consume 100% of both my CPU`s and write/read heavily
to the /usr/openv/netbackup/db filesystem.

When I have no action at all after a clean start, we have about 42 bpdbm
processes and nearly as many bprd processes


 

I cant figure this one out, and support points to disk config or something
else that sounds good in there ears


 

Thanks for all help,

 

Hampus Lind
Rikspolisstyrelsen
National Police Board
Tel dir: +46 (0)8 - 401 99 43
Tel mob: +46 (0)70 - 217 92 66
E-mail: hampus.lind at rps.police.se

-----Ursprungligt meddelande-----
Fr?n: Bahnmiller, Bryan [mailto:BBahnmiller at pier1.com] 
Skickat: den 14 februari 2007 20:04
Till: Hampus Lind
?mne: RE: [Veritas-bu] Serious master issue...

 

Hampus,

 

  How quickly does this behaviour start happening after a recycle/reboot? I
worked with an N4000 master running 11i. We did have 8 cpus and 8 GB RAM. We
were running over 15,000 backup jobs daily though. Our catalog was over
400GB. (Catalog was on EMC DMX disk.) Running good old 3.4 we would have to
reboot the system almost every week. If you can cleanly re-cycle NetBackup -
shut it down, kill all NBU processes, and then restart it, that should be
almost as good.

 

  Here we are running NBU 5.1mp4 on a Win2K3 master - 2 cpus, 4 GB RAM. (I
inherited the system - not my choice.) We run about 5000 jobs per day, we
have a 280 GB catalog on EMC Clariion. The system will stay stable for 2
weeks pretty easily. 4 weeks starts pushing things. So we usually reboot our
Windows master and media servers every 2 weeks.

 

  It seems like you will have cumulative problems with NetBackup that can
build up over time. It is way more pronounced on busy systems. We have
another NetBackup system that has 1 Master and 1 Media server. It runs about
40 jobs per day max. I hardly ever have to reboot those servers.

 

       Bryan

 

Bryan Bahnmiller

ISD Business Continuity

Pier 1 Imports, Inc

817-252-8570

 

 


  _____  


From: veritas-bu-bounces at mailman.eng.auburn.edu
[mailto:veritas-bu-bounces at mailman.eng.auburn.edu] On Behalf Of Hampus Lind
Sent: Wednesday, February 14, 2007 12:17 PM
To: Veritas-bu at mailman.eng.auburn.edu
Subject: Re: [Veritas-bu] Serious master issue...
Importance: High

All,

 

Now I have been transferred to USA support
 God bless America!

 

They have told me that they haven?t seen such a big installation in over a
year
. Strange, I have about 200 clients and backup a couple a TB per day..
I was under the impression that this was kinda small installation..??

 

However, they have told me that this is perfectly normal behaviour with
netbackup. That it produces heavy disk IO and eat all CPU power. And I was
really stupid and told them that I also had an case with HP earlier on this
disk IO problem, so now Symantec support are pointing all there fingers at
HP and our disk setup.

 

Our DB is about 60-65 GB and resides on a StorageTek Flexline 380 disk array
(SAN). We run a RAID 5 on 146GB FC drives.. I don?t really see the
bottleneck there, but I will create a RAID 5 on 73GB 15K FC drives just to
shut netbackup support up


 

We run a two CPU HP rp2470  with HP-UX 11.11 as a master server. Shouldn?t
this be enough for this installation?

 

Ooh well
 

 

If support cant help me, what should I do?? I am desperate!!!

 

 

Hampus Lind
Rikspolisstyrelsen
National Police Board
Tel dir: +46 (0)8 - 401 99 43
Tel mob: +46 (0)70 - 217 92 66
E-mail: hampus.lind at rps.police.se

-----Ursprungligt meddelande-----
Fr?n: veritas-bu-bounces at mailman.eng.auburn.edu
[mailto:veritas-bu-bounces at mailman.eng.auburn.edu] F?r Hampus Lind
Skickat: den 14 februari 2007 12:48
Till: Veritas-bu at mailman.eng.auburn.edu
?mne: [Veritas-bu] Serious master issue...
Prioritet: H?g

 

Hi,

 

We have a serious issue here with our master server. The problem occurred a
couple of weeks ago, or at least I found out about it then..

 

I was looking at IO`s and scsi queue depth on my master (hp-ux 11.11) when a
say that we had 4000-6000 SCSI commands in que, and a disk utilisation of
100% for the /usr/openv/netbackup/db disk.

 

I have patched hpux to the latest patch bundle and we run NBU 5.1 MP4.

 

HP support sad that bpdbm was leaking memory.

 

Veritas support still investigating.. But we have about 30 bpdbm and bprd
processes active on our master which eats both my CPU`s and produces tons of
IO against our db disk.

 

I actived verbose = 5 on the master, and after 15 minutes the bpdbm log had
reached the file size limit on our filsystem, 2 GB


 

Any one had similar problems? 

 

 

Thanks and regards,

 

Hampus Lind
Rikspolisstyrelsen
National Police Board
Tel dir: +46 (0)8 - 401 99 43
Tel mob: +46 (0)70 - 217 92 66
E-mail:  <mailto:hampus.lind at rps.police.se> hampus.lind at rps.police.se

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: 