The Amanda planner schedules a level 0 of a DLE on the "due" date.
To see which one that is, do "amadmin config due".
Then Amanda looks at the total amount of level 0's, and compares
it to the "balanced" amount (total amount / runspercycle).
If the amount is less then balanced, Amanda will try to "promote"
some level 0's that are due the next few days, to run this day.
The "maxpromotedays" means that Amanda will not promote this DLE
more than this numbers of days in advance.
Thanks, now I understand. I think I leave my smaller DLEs with their
defaults and set the maxpromotedays for some larger DLEs to 2.
--