running backup + expire at the same time
1999-08-26 03:46:38
Hi,
I have read in several mails that problems may occur, when migration- , backup
and reclamation processes are running at the same time. ( I also have
problems with deadlocks, and IBM told me too to start expire and backup at
different times) But I have not found any documentation where this is
discribed. The scheduler of ADSM doesn't support the definition of
dependencies, so I only have the chance to start the processes at different
times. This is not a good solution.
IBM should document which procceses are allowed to run at the same time and the
scheduler should support dependencies or resource-controlling like other
schedulers (OPC or control m).
What are you thinking about that?
regards winfried
|
<Prev in Thread] |
Current Thread |
[Next in Thread>
|
- running backup + expire at the same time,
Winfried Heilmann <=
|
|
|