Thanks Bobby,
This seems to be the answer to my question. I shall ensure that the
Monthly backups run 30 min earlier than the "normal" Weekly schedules.
Regards
Andrew Wilkin
Computer Systems Analyst
Department of Lands
Panorama Ave
BATHURST, NSW, 2795, AUSTRALIA
Ph: 61 2 6332 8397
Fx: 61 2 6332 8457
E-mail: Andrew.Wilkin at lands.nsw.gov.au
WEB: www.lands.nsw.gov.au <http://www.lands.nsw.gov.au>
________________________________
From: Bobby Williams [mailto:bobbyrjw at bellsouth.net]
Sent: Monday, 31 July 2006 8:28 PM
To: Andrew Wilkin; veritas-bu at mailman.eng.auburn.edu
Subject: RE: [Veritas-bu] Calender Question
Yes, it is. The thing that you have to do is to keep the monthly
schedule in the same policy as the weekly full. Just have your start
time for the monthly start "wakeup interval" before the full weekly
backup. That will help you start the monthly before the weekly full.
The scheduler (when working properly) checks to see what schedule in the
policy has not been run the most recently and plans to run it. It then
checks (still only in the same policy) to see if a backup of the same
type (FULL/INCR) has run within the scheduled time period.
If the monthly is in a different policy, then it will run regardless of
the weekly full.
Bobby Williams
2205 Peterson Drive
Chattanooga, Tennessee 37421
423-296-8200
________________________________
From: veritas-bu-bounces at mailman.eng.auburn.edu
[mailto:veritas-bu-bounces at mailman.eng.auburn.edu] On Behalf Of Andrew
Wilkin
Sent: Monday, July 31, 2006 1:31 AM
To: veritas-bu at mailman.eng.auburn.edu
Subject: [Veritas-bu] Calender Question
Hi Forum,
I'm configuring a backup that has 3 different schedules.
Daily, retention period 1 month, runs daily
Weekly, retention period 1 month, runs every Friday
Monthly, retention period 1 year, runs last Friday of the month
However what happens when I want the Weekly to run every Friday (all
Fridays checked, in Weekly schedule), but if it's say the 4th Friday
(and that is the last Friday of the month) e.g. August 2006, is
NetBackup "smart" enough to run a Monthly backup if the Monthly schedule
has "Last Friday" checked, and not run the normal Weekly Backup
Thanks
Regards
Andrew Wilkin
Computer Systems Analyst
Department of Lands
Panorama Ave
BATHURST, NSW, 2795, AUSTRALIA
Ph: 61 2 6332 8397
Fx: 61 2 6332 8457
E-mail: Andrew.Wilkin at lands.nsw.gov.au
WEB: www.lands.nsw.gov.au <http://www.lands.nsw.gov.au>
***************************************************************
This message is intended for the addressee named and may contain
confidential information. If you are not the intended recipient, please
delete it and notify the sender.
Views expressed in this message are those of the individual sender, and
are not necessarily the views of the Department of Lands.
This email message has been swept by MIMEsweeper for the presence of
computer viruses.
***************************************************************
-------------- next part --------------
An HTML attachment was scrubbed...
URL:
http://mailman.eng.auburn.edu/pipermail/veritas-bu/attachments/20060801/96943a0b/attachment-0001.html
|