Hi
Got a customer with huge amounts of data. Backup is going to three
advanced filedevices, and staged to tape. The staging is taking so
long, that it runs well into his production hours. Because of that, he
is not able to do restores from the filedevices. I know that this is a
limitation in NetWorker, but has anyone found a workaround.
Backupserver is Windows 2000, filedevice is on a storagenode also
running Windows 2000, he has 6 SDLT drives for the staging.
Best regards
Tore Eikanger
Senior Systems Engineer
______________________________
Ementor Norge AS, Solheimsgaten 18, Box 7370, NO-5020 Bergen
Tel +47 55 59 55 00, Dir +47 55 59 55 22, Mobile +47 930 55 876
tore.eikanger AT ementor DOT no <mailto:tore.eikanger AT ementor DOT no>
www.ementor.no <http://www.ementor.no>
--
Note: To sign off this list, send a "signoff networker" command via email
to listserv AT listmail.temple DOT edu or visit the list's Web site at
http://listmail.temple.edu/archives/networker.html where you can
also view and post messages to the list. Questions regarding this list
should be sent to stan AT temple DOT edu
=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=*=
|