Michael,
I thought the default is 1.
PERiod
Specifies the length of time between startup windows for this
schedule.
This parameter is optional. This parameter is used only with classic
schedules. You can specify an integer from 1 to 999. The default is 1.
Use this parameter with the PERUNITS parameter to specify the period
between startup windows. For example, if you specify PERIOD=5 and
PERUNITS=DAYS (assuming that DAYOFWEEK=ANY), the operation is
scheduled
every five days after the initial start date and start time. The
period
between startup windows must exceed the duration of each window. The
default is 1 day.
This value is ignored if you specify PERUNITS=ONETIME.
Avy Wong
Business Continuity Administrator
Mohegan Sun
1 Mohegan Sun Blvd
Uncasville, CT 06382
(860)862-8164
(cell) (860)961-6976
Michael Green
<mishagreen@GMAIL
.COM> To
Sent by: "ADSM: ADSM-L AT VM.MARIST DOT EDU
Dist Stor cc
Manager"
<[email protected] Subject
.EDU> Re: [ADSM-L] scheduling
11/20/2007 01:50
AM
Please respond to
"ADSM: Dist Stor
Manager"
<[email protected]
.EDU>
Shouldn't it be:
upd sched standard 2100_something dur=59 duru=minutes period=1 peru=hours
???
On Nov 19, 2007 11:14 PM, Mcnutt, Larry E. <larry.mcnutt AT timken DOT com>
wrote:
> Avy,
>
> Something like the following is what you could do to change it to run
> hourly. This assumes that it can complete in less than an hour,
> otherwise sometimes you will get a "missed" backup for those times that
> run longer than an hour.
>
> Update schedule standard 2100_something duration=15 durunits=minutes
> perunits=hours
>
> Larry McNutt
>
>
>
> -----Original Message-----
> From: ADSM: Dist Stor Manager [mailto:ADSM-L AT VM.MARIST DOT EDU] On Behalf
> Of
> Avy Wong
> Sent: Monday, November 19, 2007 3:57 PM
> To: ADSM-L AT VM.MARIST DOT EDU
> Subject: scheduling
>
> Hello,
>
> Can you tell me how to update the schedule to run a backup every
> hour
> ? thanks for your help.
>
> From the client side:
>
> Schedule name: 2100_somename
> Description:
> Schedule Style: Classic
> Action: Incremental
> Options: -subdir=yes
> Objects:
> Priority:5
> Next Execution: 23 Hours and 17 Minutes ( <-- I would like this to
> change
> to 60 minutes )
> Duration: 1Hour
> Period: 1 Day
> Day of Week: Any
> Month:
> Day of Month:
> Week of Month:
> Expire: Never
>
> From the server side:
>
> Policy Domain Name: STANDARD
> Schedule Name: 2100_somename
> Description:
> Action: Incremental
> Options: -subdir=yes
> Objects:
> Priority: 5
> Start Date/Time: 11/19/2007 14:39:41
> Duration: 1 Hour(s) ( <-- this is just the open
> window
> allowed)
> Schedule Style: Classic
> Period: 1 Day(s)
> Day of Week: Any
> Month:
> Day of Month:
> Week of Month:
> Expiration:
> ast Update by (administrator): WONGAV
> Last Update Date/Time: 11/19/2007 14:50:35
> Associated Nodes: SomeNode
> Managing profile:
>
> Avy Wong
> Business Continuity Administrator
> Mohegan Sun
> 1 Mohegan Sun Blvd
> Uncasville, CT 06382
> (860)862-8164
> (cell) (860)961-6976
>
> -----------------------------------------
> This message and any attachments are intended for the individual or
> entity named above. If you are not the intended recipient, please
> do not forward, copy, print, use or disclose this communication to
> others; also please notify the sender by replying to this message,
> and then delete it from your system. The Timken Company / The
> Timken Corporation
--
Warm regards,
Michael Green
|