Re: reclaimation process question
2002-11-13 08:54:11
thanks
if you have 4 storage pools and only 4 drives
would you have to use a script to control the reclaimation processes
sequentially or would you just schedule them hours apart
----- Original Message -----
From: "Schaub Joachim Paul ABX-PROD-ZH" <joachim.schaub AT ABRAXAS DOT CH>
To: <ADSM-L AT VM.MARIST DOT EDU>
Sent: Wednesday, November 13, 2002 8:26 AM
Subject: AW: reclaimation process question
no this is not correct, 1 process per pool
greets
joachim
-----Urspr|ngliche Nachricht-----
Von: Tim Brown [mailto:tbrown AT CENHUD DOT COM]
Gesendet: Mittwoch, 13. November 2002 14:24
An: ADSM-L AT VM.MARIST DOT EDU
Betreff: reclaimation process question
is it true that the tsm server can only process one reclacamation process at
any one time
so if 2 storage pools require reclaimation then the 2nd storage pool will be
reclaimed after the
first storage pool is recalimed and not simultaneously
the server
Tim Brown