Le 03/10/2011 16:05, Phil Stracchino a écrit :
On 10/03/11 08:38, Piotr Lemiesz wrote:
Hi,
I have about 30 jobs scheduled at 00:00 at priority 10
I have 1 job scheduled at 02:00 at priority 9
Maximum Concurrent Jobs = 3
Allow Mixed Priority = yes (in JobDefs)
My intention was to get this "priority 9 job" as close as it is
possible to 02:00.
But with my recent configuration it start as a last job.
I thought that the use of "Allow Mixed Priority" somehow pushes this
"priority 9 job" right after ending one of "priority 10 job" (which
ended after 02:00), but I was wrong.
Is it possible to set somehow this "priority 9 job" to run close to 02:00 ?
By the sound of things, not without increasing your job concurrency. If
you're starting 30 jobs at 00:00, and allowing only 3 of them to run at
once, then they will have to complete in roughly 12 minutes each if you
want your scheduled 02:00 job to be able to start on time.
Using more fined grained scheduling policy instead of spooling 30
jobs at a time, and lowering the number of concurrent jobs would
help you ahve your jobs started closer to the original schedule
time...
I can hardly see any other solution.
regards
--
Alexandre Chapellon
Ingénierie des systèmes open sources et
réseaux.
Follow me on twitter: @alxgomz
|
------------------------------------------------------------------------------
All the data continuously generated in your IT infrastructure contains a
definitive record of customers, application performance, security
threats, fraudulent activity and more. Splunk takes this data and makes
sense of it. Business sense. IT sense. Common sense.
http://p.sf.net/sfu/splunk-d2dcopy1 _______________________________________________
Bacula-users mailing list
Bacula-users AT lists.sourceforge DOT net
https://lists.sourceforge.net/lists/listinfo/bacula-users
|