[ADSM-L] DB2/Oracle backup reporting and scheduling
2015-03-06 12:13:17
I assume someone has dealt with this I would like to hear how they handled it.
The issue:
DB2 and/or Oracle database backups that are dependent on completion of external
processes.
Currently our DBA's utilize a variety of methods to initiate DB2 and Oracle
database backups (CRON, external schedulers, etc) which presents challenges to
confirm that they are being completed as expected. As a start, I proposed
creating a client schedule and using the TSM scheduler to trigger these events,
which would minimally provide a completed/missed/failed status. Complemented by
routine reporting of stored objects it would give me some assurance that TSM
had what it needed to assure their recovery.
The DBA's are pushing back (surprise!) claiming that "some" backups have
special requirements, such as not running during other tasks like payroll
processing, runstats, etc. so they use the external scheduler to set
"conditions" that are met before the backup is initiated.
The question proposed to me is can a TSM schedule be triggered by the external
scheduler once the conditions have been met?
I would be grateful to hear how others handle this, or if they use a different
approach altogether to assure all DP database backups are completing on a
timely basis.
TIA
~Rick
|