I am not too sure about resets, but that way one could control and
minimize the # of tapes go offsite would be to use MAXPRocess.
Lower the Maxprocess #, less tape mounts thus can minimize # of tapes that
go offiste.
Sung Y. Lee
"ADSM: Dist Stor Manager" <ADSM-L AT VM.MARIST DOT EDU> wrote on 10/31/2005
02:16:01 PM:
> Hey!
>
> In an effort to minimize the number of tapes that go off site, is there
> an option that I can add to the backup stg command to copy everything in
> the primary pool to the copy pool, and resets the previous copy, and
> creates a new copy?
>
> Thanks!
|