[Veritas-bu] 213 error for multiple copies, different storage units
2006-08-22 13:28:00
Subject: |
[Veritas-bu] 213 error for multiple copies, different storage units |
From: |
ddobbs at mutualmaterials.com (Dan Dobbs) |
Date: |
Tue, 22 Aug 2006 10:28:00 -0700 |
Greetings, list.
Currently, I have a policy that makes two copies: one goes to the SAN
for near-line, one goes to tape for offsite. Last weekend, my tape drive
failed, but the entire job failed with a 213.
Shouldn't the SAN copy have worked? It's set to 'continue' in the
schedule. Or, does a 213 fail both, regardless?
Thanks for any replies!
-dd
-Dan Dobbs, System Administrator, RHCT
-Mutual Materials
-425.452.2387
|
<Prev in Thread] |
Current Thread |
[Next in Thread> |
- [Veritas-bu] 213 error for multiple copies, different storage units,
Dan Dobbs <=
|
|
|