Re: Backup completed succesfully after being cancelled?
2004-12-07 14:30:14
From: ADSM: Dist Stor Manager [mailto:ADSM-L AT VM.MARIST DOT EDU] On
Behalf Of Timothy Hughes
>I Canceled an active backup session due to a possible problem,
>There were two sessions active of the this node. I canceled
>both then did a a q session and it was not there. Yet when I
>look in the TSM server log it showed that the node completed
>successfully? It also shows the backup completed successfully
>when I display in operational results.
>
>What would be possible reason that a backup would complete
>successfully after being canceled. FYI: the backup did not
>complete before I cancelled it.
The SUCCESSFUL listing you see reflects the fact that the scheduled
backup began successfully. There is no "official" posting as to the
success or failure of a manual backup.
>12/07/04 12:07:10 ANR2507I Schedule MIDNIGHT for domain PRODUCTION
>started at 12/07/04 00:00:01 for node SPVAMER completed successfully at
>12/07/04 12:07:10. (SESSION: 3275)
See?
--
Mark Stapleton (stapleton AT berbee DOT com)