Thanks R. i have this guide with me but i don't know i m lost somewhere.
Like the questions are:
1- "how I can automate checkouts of copy storage pool tapes"
2- "when i bring back the tapes to onsite, and checkin into library would it
reuse it for backup of
primary stg. pool on these tapes or it would go for scratch volumes?"
3- "if i keep reuse delay of 3 then should i b able to use the tapes sent to
offsite as scratch volumes
or what?"
Sandra
CORP Rick Willmore wrote:
> http://www.redbooks.ibm.com/redbooks/pdfs/sg246844.pdf
>
> I also found a lot of the necessary details for DRM in the Administrator's
> guide.
> http://sp81.msi.umn.edu:999/sys_manuals/tsm/aix/guide/a72agd02.htm
>
> If you want I can email the guide to you offlist. I just popped this guide
> link up really quickly.
>
> R.
>
> -----Original Message-----
> From: Sandra [mailto:sadi AT SUPER.NET DOT PK]
> Sent: Monday, September 27, 2004 10:38 AM
> To: ADSM-L AT VM.MARIST DOT EDU
> Subject: Re: please help -- DRM -- 3582 Library with 2 drives -- Need
> assistance
>
> PLEASE I NEED ASISTANCE .. CAN ANYONE HELP ME OUT OF THIS???
>
> Sandra
>
> Sandra wrote:
>
> > Dear List,
> > I have installed the TSM extended edition 5.2.2 with patch 5.2.2.5 and
> > maintenance 5.2.3. I have Library setup and backups are being done on tapes
> > in
> > tape library. I am not running collocation. Operating system is Windows 2000
> > with SP-4.
> >
> > What I have done :?
> > *****
> > I have checked in 6 tapes:
> > 000001 000002 000003 000004 000005 000006
> > Currently backup is available on tape 000001, that is the only tape volume
> > defined in LTOPOOL1.
> >
> > I have backedup LTOPOOL1 to CPPOOL1 with DRM setup.
> > I have reuse delay of 3, that is I will reuse tape 000002 on 4th day from
> > today.
> >
> > ******
> >
> > What I want:?
> > 1- How do I checkout tape 000002 to be taken to backup site?
> > 2- How do I track back that I need to take volume 000002 to main site and
> > reuse?
> > That is how do i know the cycle of these tapes?
> >
> > 3- Does anyone have any DRM Plan, a small one so that I get to know the
> > details
> > of DAILY operations?
> >
> > I am confused with expire inventory process, how do I initiate it and when?
> >
> > Cheers,
> > Sandra.
|