Hi TSM gurus,
Here is an example from
"Operation view
- Monitor operations
- Examine client schedule event records
- Operation Results" with detailed selected:
Policy Domain Name: STANDARD
Schedule Name: BKP_00_30_INCREMENTAL
Node Name: PROD
Scheduled Start: 04/17/2004 00:30:00
Actual Start: 04/17/2004 00:30:14
Completed:
Status: (?)
Result:
According to
http://publib.boulder.ibm.com/tividd/td/ITSML/GC23-4691-02/en_US/HTML/anrlrf522257.htm
The valid status are: Completed, Failed, Future, In Progress, Missed,
Pending, Restarted, Severed, Started, Uncertain but there is nothing about
(?).
How should the (?) be handle ?
Can this backup be considered successful?
Thanks,
Jean-Pierre Denis
WebGlobe - IT Solutions
Email: jp AT webglobe DOT ca
Phone: (819) 246-0WWW (0999)
Web: http://www.webglobe.ca
|