Re: V5.1.8.0 server on z/OS
2003-11-12 02:13:52
Hi,
at the moment we are migrating from 5.1.6.3 to 5.2.1.1 on z/OS (But we are not
migrating to 5.1.8 first).
After upgradedb of the first server we had a huge problem with the performance
and IBM told us to ZAP our DSMSERV module in the linklib (APAR PQ80211).
Now everything works fine and I can upgrade the rest of our TSM-Servers ;-)
regards
Joachim Stumpf
------------- Original-Nachricht folgt -------------
I was planning to upgrade my z/OS server to 5.1.7 when 5.1.8 came out (I
want to go to 5.2.x but need to figure out what I need to do to get the
tapes since the ftp site only seems to include patches to 5.2.x).
I have installed this upgrade to my test server and so far so good !
Anyone performed this update, already ?
Any problems jumping from 5.1.6.4 to 5.1.8.0 ? (yes, I realize an
UPGRADEDB is required !) ? When I upgraded my test server, I jumped from
5.1.6.4 to 5.1.7.0 and then to 5.1.8.0.
|
|
|