What about two schedules
- one running daily with Objects set to S:
- one running on Fridays with Object set to D:
Even if they are set to same startup time, TSM scheduler is smart enough
to start them in sequence. Or simply set 5 min difference between them.
You can still bind all D: contents to a mgmtclass with frequency of 7 days
using Andy's include syntax.
Zlatko Krastev
IT Consultant
Please respond to "ADSM: Dist Stor Manager" <ADSM-L AT VM.MARIST DOT EDU>
Sent by: "ADSM: Dist Stor Manager" <ADSM-L AT VM.MARIST DOT EDU>
To: ADSM-L AT VM.MARIST DOT EDU
cc:
Subject: Re: Schedule Question.
The include syntax for your D: drive would be:
include d:\...\* pst_mgmt_class
But I don't think that this would work very well since there is almost
certainly no guarantee that everything on D: changes every Friday, in
lock-step
A couple of possibilities:
1) Create schedules for Monday, Tuesday, Wednesday, Thursday, Friday, and
Weekend. For the Friday schedule, set the OBJECTS parameter to D: S:. For
the other schedules, set OBJECTS to S: only.
2) Create a single schedule with OBJECTS="D: S:". Then create two Admin
schedules:
- One to issue UPDATE SCHEDULE for the client schedule that sets
OBJECTS="D: S:". Schedule this to run just before the Friday backup.
- One to issue UPDATE SCHEDULE for the client schedule that sets
OBJECTS="S:". Schedule this to run before the Saturday backup.
Regards,
Andy
Andy Raibeck
IBM Software Group
Tivoli Storage Manager Client Development
Internal Notes e-mail: Andrew Raibeck/Tucson/IBM@IBMUS
Internet e-mail: storman AT us.eyebm DOT com (change eye to i to reply)
The only dumb question is the one that goes unasked.
The command line is your friend.
"Good enough" is the enemy of excellence.
"Gent, Chad E." <cgent AT LEGGMASON DOT COM>
Sent by: "ADSM: Dist Stor Manager" <ADSM-L AT VM.MARIST DOT EDU>
09/19/2002 06:45
Please respond to "ADSM: Dist Stor Manager"
To: ADSM-L AT VM.MARIST DOT EDU
cc:
Subject: Schedule Question.
Hello All,
NT 4 Client with TSM 4.2.15
Server AIX 4.3.3 TSM 4.2.11.14
I have a client with 2 drives; D: and S:. I need everything on the D:
drive
to only be backed up on Fridays. But I need the S: drive to continue
doing
a daily backup. What is the best way to accomplish this scenario?
1. Create a management class with a frequency of 7 and assign this
management class to the entire D: drive. But if I use this option how do
I
assign the entire D: drive to this management class in my client option
file?
Include "D:" PST_MGMT_CLASS
Or
2. Is there a way to create a schedule on the Server and have that
schedule
use a particular option file on the client?
Thanks
Chad
|