i have a question concerning the ADSM scheduler. I was looking for >>the
feature to say that a backup should run "Mon to Wed and Fri" in >>one
schedule.
But it seems that this is not possible. So i have to create several
schedules, one for each day.

We solve a similar problem to this by resetting the startdate of the
schedule to "today+2" each Wednesday (after the Wednesday schedule >has
run!).
With the ADSM server running on AIX, we do this via a cron job
Regards,
Bob Douglas
Oxford University Computing Services

Although this won't do a run 3, skip 1, run 1 scenario as easily as Bob's
suggestion, another way to tackle running a schedule when you want it would
be to update the schedule duration units to hours and then set the schedule
duration to 48 for every 2 days, 72 for every 3 days, etc. Unexpected boots,
or anything else causing the scheduler process to recycle, would cause a
little trouble though! Scheduling client scheduler stop/start via NT at or
Unix cron could be used to re-sync.