Good morning / afternoon folks.
A new implementation of DP for VE (VMware) using SP 8.1.0 at both Server & Client/TDP level.
Vmware environemnt is at level 6.5 [ESXi & vSphere] VM Version 13
During testing of a scheduled vm backup I am expereincing the exact same scheduler hanging symptoms & ANR failures as described in the IBM article below.
http://www-01.ibm.com/support/docview.wss?uid=swg21988464
http://www-01.ibm.com/support/docview.wss?uid=swg21988464
According to this article the problem can affect vm's with a vmware tools level below 10.0.9 & VMware have addressed this with a fix applied at the 10.0.9 level.
The vm I am using for testing is at the (current) level of 10272 (which equates to 10.1.0) with a status of 'running'
https://packages.vmware.com/tools/versions
Just wanted to touch base with the TSM/SP community here to see if anyone else has experienced this before I go to IBM with this issue?
Thanks
A new implementation of DP for VE (VMware) using SP 8.1.0 at both Server & Client/TDP level.
Vmware environemnt is at level 6.5 [ESXi & vSphere] VM Version 13
During testing of a scheduled vm backup I am expereincing the exact same scheduler hanging symptoms & ANR failures as described in the IBM article below.
http://www-01.ibm.com/support/docview.wss?uid=swg21988464
http://www-01.ibm.com/support/docview.wss?uid=swg21988464
According to this article the problem can affect vm's with a vmware tools level below 10.0.9 & VMware have addressed this with a fix applied at the 10.0.9 level.
The vm I am using for testing is at the (current) level of 10272 (which equates to 10.1.0) with a status of 'running'
https://packages.vmware.com/tools/versions
Just wanted to touch base with the TSM/SP community here to see if anyone else has experienced this before I go to IBM with this issue?
Thanks