[Veritas-bu] Staging off Virtual Tape Library
2010-07-13 15:19:44
The person before me had configured a large backup policy (4TB) to have
Multiple Copies. 1 copy goes to our virtual tape library (VTL) with a 2-week
retention and the 2nd copy goes to our physical tape library with a 2-month
retention. Obviously the VTL is there in case of a huge disaster we can have a
faster recovery.
The problem I notice is, in this configuration, Netbackup wants a VTL and TLD
tape drive at the same time to do this backup so that it can stream the data to
both destinations at the same time.
I would much rather backup to the VTL during our nightly backup window and then
let it duplicate to the physidal library during the day. Can I set this up in
Netbackup or am I going to have to start writing some scripts?
I know this can be acheived with DSSU storage units as it very openly has a
"Enable Staging Schedule" button, haha. But no such option on a storage unit
pointing at a VTL....
If I have no explained something clearly, please let me know.
+----------------------------------------------------------------------
|This was sent by brandon.pawoll.ctr AT mda DOT mil via Backup Central.
|Forward SPAM to abuse AT backupcentral DOT com.
+----------------------------------------------------------------------
_______________________________________________
Veritas-bu maillist - Veritas-bu AT mailman.eng.auburn DOT edu
http://mailman.eng.auburn.edu/mailman/listinfo/veritas-bu
|
<Prev in Thread] |
Current Thread |
[Next in Thread>
|
- [Veritas-bu] Staging off Virtual Tape Library,
Brandon35 <=
|
|
|