Subject: [Veritas-bu] NetBackup Schedules - 3 Schedules in 1Policyad vice
From: KrugerC2 at telkom.co.za (Clem Kruger (C))
Date: Fri, 6 Oct 2006 14:11:24 +0200
Hi David,

What I do is to have one policy per server. Within that policy, I
setup the daily, weekly, monthly, yearly and ad-hoc backups. 

I use the calendar function to ensure that I do not have any clashes.
I sometimes set an earlier start time for the weekly, monthly etc.
where the backups my run longer.

 
 
 
Regards, 
 
Clem Kruger
Telkom SA Ltd
ITS Infrastructure Storage Management

: +27 (12) 680 3102

: +27 (12) 680 3299

: +27 (83) 326 2260

: krugerc2 at telkom.co.za
 
-----Original Message-----
From: veritas-bu-bounces at mailman.eng.auburn.edu
[mailto:veritas-bu-bounces at mailman.eng.auburn.edu] On Behalf Of
WEAVER, Simon
Sent: 06 October 2006 13:17 PM
To: 'David Rock'; veritas-bu at mailman.eng.auburn.edu
Subject: Re: [Veritas-bu] NetBackup Schedules - 3 Schedules in
1Policyad vice


David
My thoughts exactly - more so, was making sure the WINDOW for both
Monthly
and full are SET the same - otherwise I kinda thought this in itself
could
cause an issue and start off a schedule I did not want to start :-)

Thank you for your help on this matter

Regards

Simon Weaver
3rd Line Technical Support
Windows Domain Administrator 

EADS Astrium Limited, B23AA IM (DCS)
Anchorage Road, Portsmouth, PO3 5PU

Email: Simon.Weaver at Astrium-eads.net



-----Original Message-----
From: David Rock [mailto:dave-bu at graniteweb.com] 
Sent: 06 October 2006 07:01
To: veritas-bu at mailman.eng.auburn.edu
Subject: Re: [Veritas-bu] NetBackup Schedules - 3 Schedules in 1
Policyadvice


* WEAVER, Simon <simon.weaver at astrium.eads.net> [2006-10-06 06:35]:
> 
> All,
>  
> NBU 5.1 MP2 Win2k Master + 2 SAN MS
> Morning! I am trying to work out a solution to trimming down all the

> policies I have. Presently, I have the following:-
>  
> 1 x Policy for Month backups, which contains 1 Schedule. Schedule 
> starts 7pm Fri and ends 7am Sat
>  
> 1 x Policy for Weekly Backups, which contains 2 Schedules. 1 x 
> Schedule is the Full Backup, starting 7pm Fri and ends 7am Sat. The 
> next schedule is for Incr which take place 7pm - 10pm Mon, Tues, Wed

> and Thursday only.
>  
> If I was to place the MONTHLY SCHEDULE (Copy / Paste) into the
Weekly 
> Backup Policy, would I get the Monthly and Weekly full backups
trying 
> to run at the same time?
>  
> I am trying to work out the best way (and effecient) to ensure
monthly 
> runs on a set day only, but does not interfere with the regular
weekly 
> full backup.

Adding the Monthly schedule to the existing policy containing the
Weekly and
Daily schedules will not result in both running at the same time.
Frequency
based scheduling does just that, it give priority to the schedule that
runs
on the _least_ frequent schedule.  So, if there is a conflict between
the
Monthly and the Weekly, the Monthly will win. Having them in separate
policies _guarantees_ they will _always_ try to run at the same time.
Having them in the _same_ policy is specifically intended to manage it
for
you so they don't.  Of course, you will need to play with it to make
sure it
does what you think it's supposed to do
:-)

-- 
David Rock
david at graniteweb.com _______________________________________________
Veritas-bu maillist  -  Veritas-bu at mailman.eng.auburn.edu
http://mailman.eng.auburn.edu/mailman/listinfo/veritas-bu

This email is for the intended addressee only.
If you have received it in error then you must not use, retain,
disseminate or otherwise deal with it.
Please notify the sender by return email.
The views of the author may not necessarily constitute the views of
Astrium Limited.
Nothing in this email shall bind Astrium Limited in any contract or
obligation.

Astrium Limited, Registered in England and Wales No. 2449259
Registered Office: Gunnels Wood Road, Stevenage, Hertfordshire, SG1
2AS, England
_______________________________________________
Veritas-bu maillist  -  Veritas-bu at mailman.eng.auburn.edu
http://mailman.eng.auburn.edu/mailman/listinfo/veritas-bu

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
This e-mail and its contents are subject to the Telkom SA Limited
e-mail legal notice available at 
http://www.telkom.co.za/TelkomEMailLegalNotice.PDF
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


<Prev in Thread] Current Thread [Next in Thread>