I always thought you would get a 196 status (Backup Window closed). I assume
you restarted by choosing a stream that failed and right clicking on it and
selecting "restart job" ?
 
 

Regards

Simon Weaver
3rd Line Technical Support
Windows Domain Administrator 

EADS Astrium Limited, B32AA IM (DCS)
Anchorage Road, Portsmouth, PO3 5PU

Email:  <mailto:Simon.Weaver at Astrium-eads.net> Simon.Weaver at 
Astrium-eads.net

-----Original Message-----
From: Tristan Ball [mailto:Tristan.Ball at vsl.com.au] 
Sent: 14 June 2006 01:40
To: Martin, Jonathan (Contractor); veritas-bu at mailman.eng.auburn.edu
Subject: Re: [Veritas-bu] Checkpoint Restart


I've restarted streams after window closure, it seems to work OK.
 
T.
 
---
Tristan Ball
System Administrator
Vision Systems
+61-3-9211-7064
 
 

  _____  

From: veritas-bu-bounces at mailman.eng.auburn.edu
[mailto:veritas-bu-bounces at mailman.eng.auburn.edu] On Behalf Of Martin,
Jonathan (Contractor)
Sent: Tuesday, 13 June 2006 3:30 AM
To: veritas-bu at mailman.eng.auburn.edu
Subject: [Veritas-bu] Checkpoint Restart


It is my understanding that I can't "restart" a failed backup with
checkpoint enabled unless it is still in the backup window?  Is this
correct?  Also, does anyone have any tips on using checkpoint and large
backups?
 
Thanks,
 
-Jonathan

  _____  

From: veritas-bu-bounces at mailman.eng.auburn.edu
[mailto:veritas-bu-bounces at mailman.eng.auburn.edu] On Behalf Of Paul Keating
Sent: Monday, June 12, 2006 8:22 AM
To: veritas-bu at mailman.eng.auburn.edu
Subject: Re: [Veritas-bu] NetBackup Planning / DR process


keep in mind that in order for BMR to work properly, clients must be on the
same VLAN as the BMR server, in order to boot.
 
 
-- 

-----Original Message-----
From: veritas-bu-bounces at mailman.eng.auburn.edu
[mailto:veritas-bu-bounces at mailman.eng.auburn.edu] On Behalf Of WEAVER,
Simon
Sent: June 12, 2006 4:02 AM
To: 'veritas-bu at mailman.eng.auburn.edu'
Subject: [Veritas-bu] NetBackup Planning / DR process


Good Morning
Well so far, so good - got a more stable NBU system - one SAN Media failed
its backup, but not bothered about that and its running fine now!
 
I wanted to try and cover some grounds with any NBU win2k3/NT/2000
environments, about how your NetBackup environment is configured and what
failover you have in place or DR plans.
 
I have been looking at BMR for NBU6, but I run 5.1 MP2 which has been
extremely stable for us (if you exclude the manual intervention of someone
destroying it!!!), and have not been fully convinced about going to 6 yet.
 
BMR works and integrates with 6, but from a DR point, I am not sure if this
is the right method to go down.



This email is for the intended addressee only.
If you have received it in error then you must not use, retain, disseminate or 
otherwise deal with it.
Please notify the sender by return email.
The views of the author may not necessarily constitute the views of EADS 
Astrium Limited.
Nothing in this email shall bind EADS Astrium Limited in any contract or 
obligation.

EADS Astrium Limited, Registered in England and Wales No. 2449259
Registered Office: Gunnels Wood Road, Stevenage, Hertfordshire, SG1 2AS, England
-------------- next part --------------
An HTML attachment was scrubbed...
URL: 
http://mailman.eng.auburn.edu/pipermail/veritas-bu/attachments/20060614/d6018a7f/attachment-0001.html