Well I found out yesterday that it does work just fine.
I turned up my global copy level to 3, and when I opened my DSSU
properties, the "Disk staging schedule" section allowed me to create
multiple copies.

The oddity is, today, I removed the DSSU, dropped # of copies back down
to 2, tried to recreate the DSSU.....multiple copies disabled, just as
I'd expect, but when I put global copies back to 3 again, it didn't come
back.

Hmmm....

Paul

> -----Original Message-----
> From: veritas-bu-admin AT mailman.eng.auburn DOT edu 
> [mailto:veritas-bu-admin AT mailman.eng.auburn DOT edu] On Behalf Of J R
> Sent: May 25, 2005 5:00 PM
> To: veritas-bu AT mailman.eng.auburn DOT edu
> Subject: Re: [Veritas-bu] Disk staging & duplication NBU 5
> 
> 
> Well,
> 
> Doing the backup to disk and then using Vault is about
> the only way to be able to accomplish what you want to
> do. By the way, you are correct about the backup only
> going as fast(slow) as the slowest device. So the
> backups, even though one of them is going to disk,
> would slow down to the speed of the backup to the tape
> drive. It is one of the reasons they don't recommend
> doing inline tape copy to disk and tape.
> 
> Jeff
> 
> "A wise man once said 'Wherever you go, there you are'"
>       -Mike Brady