Hello all

At a customer site we faced the same problem for the second time within one 
month. 

A scheduled backup of an ndmp-policy suddenly does not start anymore. The 
schedule is calendar based with a daily window of 2 hours. The backups were 
never run manually.

However when I copy the policy to a new one the schedule starts the backups 
without any problems.

Are there any known issues with the scheduler and/or calendar based scheduling?

Environment is BusinesServer 4.5 on W2K, Procom NetForce with NDMP v.2

Thanks & regards