I believe you can just stop the request manager service (bprd).  Media
change requests for the long job should be handled by volume manager (vmd)
and device manager (ltid).

Good luck,
Matt


-----Original Message-----
From: Arne Kloecker [mailto:arne AT topnet DOT de] 
Sent: Wednesday, August 21, 2002 9:41 AM
To: veritas-bu AT mailman.eng.auburn DOT edu
Subject: [Veritas-bu] How to disable the start of new jobs


Hi,

i'm looking for a way to let the current jobs run to their end but no new 
jobs should start.

I want to have a maintenace window, but we have jobs running all the time. I

want to do some maintance work right after one long job is done, but there 
are some jobs that probably would start before the long one is finished. I 
could just disable the classes until i'm done with maintenance but i look
for 
a general "no new jobs" solution.

Any ideas ? 


Thanks in advance

Arne Kloecker
_______________________________________________
Veritas-bu maillist  -  Veritas-bu AT mailman.eng.auburn DOT edu
http://mailman.eng.auburn.edu/mailman/listinfo/veritas-bu

<Prev in Thread] Current Thread [Next in Thread>