Veritas-bu

[Veritas-bu] How to disable the start of new jobs

2002-08-21 14:14:23
Subject: [Veritas-bu] How to disable the start of new jobs
From: scott.kendall AT abbott DOT com (scott.kendall AT abbott DOT com)
Date: Wed, 21 Aug 2002 13:14:23 -0500
Stopping the Request Daemon on the master will stop any new automatic backups
from starting (and will also stop any restores or user initiated backups from
being initiated).

UNIX:  to stop:  /usr/openv/netbackup/bin/admincmd/bprdreq -terminate
UNIX:  to start:  /usr/openv/netbackup/bin/initbprd

WINDOWS: start/stop Request Manager service


- Scott



                                                                                
                                                   
                    Arne Kloecker                                               
                                                   
                    <arne AT topnet DOT de>                     To:     
<veritas-bu AT mailman.eng.auburn DOT edu>                               
                    Sent by:                             cc:                    
                                                   
                    veritas-bu-admin AT mailman DOT eng.        Subject:     
[Veritas-bu] How to disable the start of new jobs            
                    auburn.edu                                                  
                                                   
                                                                                
                                                   
                                                                                
                                                   
                    08/21/2002 08:41 AM                                         
                                                   
                                                                                
                                                   
                                                                                
                                                   




Hi,

i'm looking for a way to let the current jobs run to their end but no new
jobs should start.

I want to have a maintenace window, but we have jobs running all the time. I
want to do some maintance work right after one long job is done, but there
are some jobs that probably would start before the long one is finished. I
could just disable the classes until i'm done with maintenance but i look for
a general "no new jobs" solution.

Any ideas ?


Thanks in advance

Arne Kloecker
_______________________________________________
Veritas-bu maillist  -  Veritas-bu AT mailman.eng.auburn DOT edu
http://mailman.eng.auburn.edu/mailman/listinfo/veritas-bu





<Prev in Thread] Current Thread [Next in Thread>