Hi,
i'm looking for a way to let the current jobs run to their end but no new
jobs should start.
I want to have a maintenace window, but we have jobs running all the time. I
want to do some maintance work right after one long job is done, but there
are some jobs that probably would start before the long one is finished. I
could just disable the classes until i'm done with maintenance but i look for
a general "no new jobs" solution.
Any ideas ?
Thanks in advance
Arne Kloecker
|
|
|