[Veritas-bu] 13 day Retention Time
2001-08-07 11:23:39
Yes. Go to your favorite GUI in the Global Configuration section.
Change one of the levels to be 13 days.
Karl.Rossing AT Federated DOT CA writes:
> Hi,
>
> I am currently running a 2 week retention time on my tapes. I'm running
> into a little problem with retention times. Say a Job starts at Midnight
> and finish's writing to the tape at 4:00AM. Then when the 2 week rotation
> is done and the tapes get put back into the machine I'm not able to write
> to the tapes until 4:00am.
>
> Is there any way to setup a 13 day retention?
>
> Thanks
>
> Karl
> _______________________________________________
> Veritas-bu maillist - Veritas-bu AT mailman.eng.auburn DOT edu
> http://mailman.eng.auburn.edu/mailman/listinfo/veritas-bu
--
Larry Kingery
Computers make very fast, very accurate mistakes.
|
|
|