I'm perfroming a backup of a primary storage pool on an AIX ADSM server
v3.1.2.40 with a 3494 library attached (using 3590 drives). I have the storage
backup scheduled dialy and I want to take the backup tapes offsite every day.
If I checkout the tapes that have a 'Full' stauts (q vol) i have no problems,
but if I checkout tapes with a 'Filling' status the server prompts for these
volumes to be checked in. Is there any problem if i keep the volumes offsite or
do i need to check them in until they got filled?
Thanks in advance
Regards
Gerardo Zapata Gonzalez
Tivoli Professiona Services/TSM
IBM de Mexico
(52 5) 270 5740
|