Re: Multi-threaded ADSM
1997-12-09 11:21:54
You can multithread some operations on the server - but not others, for
example:
upd stg <pool> hi=0 lo=0 migpr=4 - will run 4 concurrent migration processes
backup stg <from-pool> <to-pool> migpr=2 - will run 2 concurrent processes
You can't multithread expiration or reclamation at this time (and as far as I
know) there are no plans yet to do so.
Regards, Sheelagh
------------------------------------------------------------------------------
Sheelagh Treweek Email: sheelagh.treweek AT oucs.ox.ac
DOT uk
Sheelagh Treweek Email: sheelagh.treweek AT oucs.ox.ac
DOT uk
Oxford University Computing Services Tel: +44 (0)1865 273205
13 Banbury Road, Oxford, OX2 6NN, UK Fax: +44 (0)1865 273275
------------------------------------------------------------------------------
> From owner-adsm-l AT VM.MARIST DOT EDU Tue Dec 9 15:54:44 1997
> From owner-adsm-l AT VM.MARIST DOT EDU Tue Dec 9 15:54:44 1997
> Mime-Version: 1.0
> Content-Transfer-Encoding: 7bit
> Content-MD5: YVQscIKODRiC4NQtv2gMUw==
> Date: Tue, 9 Dec 1997 10:33:00 -0500
> From: rob lalonde <lalonde AT CORP.RIVERWOOD DOT COM>
> Subject: Multi-threaded ADSM
> To: ADSM-L AT VM.MARIST DOT EDU
>
> Someone was asking about how to run more than one process or thread in a
backup.
> I was wondering if there is any way to multi-thread other parts, such as
> multiple migration processes or maybe copy and expiration processes.
>
> -Rob LaLonde
> lalonde AT corp.riverwood DOT com
>
|
Previous by Date: |
Re: Multi-threaded ADSM, Prather, Wanda |
Next by Date: |
Re: Definitely FAQ: ADSM log monitor, Prather, Wanda |
Previous by Thread: |
Re: Multi-threaded ADSM, Prather, Wanda |
Next by Thread: |
Re: "ANR2020E Invalid parameter - ORIGINATOR". ressource consump., Lambelet,Rene,VEVEY,FC-SIL/INF. |
Indexes: |
[Date]
[Thread]
[Top]
[All Lists] |
|
|