I am running 7.1 and 7.5 NBU I am have VSS and Shadow Copy problems with the 
NBU hanging on backup. With SQL and Hyper-V fighting for the same Shadow 
resources how can you schedule without the conflict. Instead of a timed 
schedule release is there an event scheduling available, i.e. when one job 
completes it kicks off the next?