[Veritas-bu] Storage life cycle policy question.
2010-07-19 15:12:26
I just accomplished something similar. If you want to follow along what I did
here is the forum:
http://www.backupcentral.com/phpBB2/two-way-mirrors-of-external-mailing-lists-3/symantec-netbackup-18/staging-off-virtual-tape-library-106811/
basically my solution was to run a script before the weekend backups would run.
the script would deactivate the duplication portion during the weekend. and
then Monday morning another script would re-activate the duplication portion
and it would begin immediately then. Thus letting you schedule that third stage
when you wanted.
+----------------------------------------------------------------------
|This was sent by brandon.pawoll.ctr AT mda DOT mil via Backup Central.
|Forward SPAM to abuse AT backupcentral DOT com.
+----------------------------------------------------------------------
_______________________________________________
Veritas-bu maillist - Veritas-bu AT mailman.eng.auburn DOT edu
http://mailman.eng.auburn.edu/mailman/listinfo/veritas-bu
|
<Prev in Thread] |
Current Thread |
[Next in Thread> |
- [Veritas-bu] Storage life cycle policy question.,
Brandon35 <=
|
|
|