From: jpiszcz.backup AT gmail DOT com (Justin Piszcz)
Date: Sat, 13 May 2006 12:54:45 -0400
One comment - running all fulls on the weekend is an extremely bad
practice, if something happens on Friday, then you lose a week's worth
of data, depending on your incremental schedule.  A better practice is
to run Fulls each day of the week and split it up in your environment.
 When the connection is cut the jobs should fail, but I have not done
too much with DSSU/disk backups myself to comment on that part.


On 5/12/06, Hillman, Eric <Eric.Hillman AT blackrock DOT com> wrote:
>
>
>
> We start weekly backups every Friday night.  They run through Sunday.  There
> is a scheduled network outage on Saturday morning between 5am and noon.
> This will disconnect clients from the backup servers and the media servers
> from the master servers.  Can anyone recommend the best way to pause these
> jobs?  Here are the choices I'm considering:
>
> 1. Stop Netbackup daemons on all master and media servers Friday night and
> restart them after the network outage is done.  I believe this will not
> allow all backups enough time to finish by Sunday night when our next backup
> window starts
>
> 2. Don't do anything.  I'm not sure what will happed to jobs that are
> running including "User" database backups which get sent to the master
> server and run on a media server when the communication between those
> servers is gone.  Also DSSU archival to tapes may experience problems when
> communication is cut between the master server who is sending the list of
> backup images to the media server to archive to tape.
>
> 3. Login immediately prior to the network outage and kill all backup jobs,
> stop Netbackup deamons and restart deamons after the network is back up.
> This has never ended cleanly.  There's always jobs that don't stop.  I
> almost always need to do some kill -9's to get the job processes to die and
> the rest of the daemons to stop.  Also, partial images will be left on
> DSSU's which won't get removed.  When jobs get restarted, they'll eventually
> run out of disk space because Netbackup left those partial images.  Does
> anyone know of an easy way of cleaning out partial images on DSSU's?
>
> Any recommendations are helpful.  Thanks!
>  THE INFORMATION CONTAINED IN THIS MESSAGE AND ANY ATTACHMENT MAY BE
> PRIVILEGED, CONFIDENTIAL, PROPRIETARY OR OTHERWISE PROTECTED FROM
> DISCLOSURE. If the reader of this message is not the intended recipient, you
> are hereby notified that any dissemination, distribution, copying or use of
> this message and any attachment is strictly prohibited. If you have received
> this message in error, please notify us immediately by replying to the
> message and permanently delete it from your computer and destroy any
> printout thereof.