[Veritas-bu] NB Scheduler
2005-02-07 15:04:18
Subject: |
[Veritas-bu] NB Scheduler |
From: |
rob AT worman DOT org (Rob Worman) |
Date: |
Mon, 7 Feb 2005 14:04:18 -0600 |
On Mon, Feb 07, 2005 at 01:41:58PM -0600 or thereabouts, Karl.Rossing AT
Federated DOT CA wrote:
> I decided to try the NB scheduler for a new backup i setup.
>
> The backup window is set to start at 4:00PM on Sunday's to 6:00am on
> Monday. The schedule is set to run once a week with a 12 day retention for
> the tapes.
>
> The first Sunda, it worked fine. the following Tuesday, i need to run a
> manual backup which completed without incident.
>
> A week after the first backup, the job did not run. I had to submit it
> early Monday morning.
>
> A week after that, the job did not run. I again had to submit the backup
> manually.
>
> I'm wondering why the job is not being submitted on Sunda?
>
> Is it because i ran a manual backup using the same schedule used for the
> Sunda backup?
yes, your suspicion is correct.
the scheduler's decision of whether or not a schedule is due
(i.e. "has the frequency elapsed yet since it last ran") will
not ignore manual backups.
HTH
rob
|
|
|