Re: CAD Control Client scheduler
2006-10-16 09:29:40
From: "Smith, I (Ian)" <Ian.Smith AT RABOBANK DOT COM>
>Do people use the CAD to control the scheduler? Is this a good idea,
>what happens if the CAD fails?
From: ADSM: Dist Stor Manager [mailto:ADSM-L AT VM.MARIST DOT EDU] On Behalf Of
Meadows, Andrew
>It has been my experience that with cad controling the scheduler I have
>seen a increase in unexplainable misses. That being said your milage
may
>vary depending on version of tsm and the os.
On the flip side, if you make a change in the client option file, using
CAD to run the scheduler doesn't require you to stop and restart the
scheduler service to enact the change.
--
Mark Stapleton (mark.s AT evolvingsol DOT com)
Senior TSM engineer
|
|
|