Hi TSMr's
We are finally getting a P570 IBM series and upgrading our current TSM
server solution (1 server).
Point A: We currently have a Winterhawk SP frame connected TSM server with
AIX 4.3.3 and TSM 5.1.1.0
Point B: We will be going to the new P570 IBM series with AIX 5.3 and I am
wanting TSM 5.3
I have a 60 GB DB at 50% full (30 GB). Also have IBM tape library 3494
with 10 tape drives SCSI attached.
Anybody out there have any guesstament of how long to go from point A to
point B
Thank You,
Bill Rosette
Data Center/IS/Papa Johns International
WWJD
|