queryschedperiod
2004-10-06 07:25:18
Hi all,
I checked about everything I can think of, but do not succeed in changing
the
queryperiod. If I understand correctly, the "queryschedperiod 12" in
the
dsm.sys file should do the job, but it always reverts to 4 hours.
I assume it is something dumb...
Regards,
Geert
dsm.sys:
compression yes
Editor yes
passwordaccess generate
queryschedperiod 12
schedlogname /tmp/dsmsched.log
schedlogretention 6 D
errorlogname /tmp/dsmerror.log
errorlogretention 6 D
dsmsched.log:
10/06/2004 13:24:42 Querying server for next scheduled event.
10/06/2004 13:24:42 Node Name: DOMINO
10/06/2004 13:24:42 Session established with server SERVER1: Linux/i386
10/06/2004 13:24:42 Server Version 5, Release 1, Level 8.3
10/06/2004 13:24:42 Server date/time: 10/06/2004 13:24:46 Last access:
10/06/2004 13:22:26
10/06/2004 13:24:42 --- SCHEDULEREC QUERY BEGIN
10/06/2004 13:24:42 --- SCHEDULEREC QUERY END
10/06/2004 13:24:42 Next operation scheduled:
10/06/2004 13:24:42
------------------------------------------------------------
10/06/2004 13:24:42 Schedule Name: LOTUSNOTES
10/06/2004 13:24:42 Action: Incremental
10/06/2004 13:24:42 Objects:
10/06/2004 13:24:42 Options:
10/06/2004 13:24:42 Server Window Start: 21:05:00 on 10/06/2004
10/06/2004 13:24:42
------------------------------------------------------------
10/06/2004 13:24:42 Schedule will be refreshed in 4 hours.
|
|
|