Re: POSTSCHEDULECMD Timing
2004-03-17 12:56:42
The POSTSCHEDULECMD should not run until the scheduled operation has
completed. Of course, if the scheduled operation launches a process that
runs in the background (asynchronously), then you are likely to see the
situation you describe since the client has no means of monitoring
background processes.
Do you have a dsmsched.log file that illustrates this problem?
Regards,
Andy
Andy Raibeck
IBM Software Group
Tivoli Storage Manager Client Development
Internal Notes e-mail: Andrew Raibeck/Tucson/IBM@IBMUS
Internet e-mail: storman AT us.ibm DOT com
The only dumb question is the one that goes unasked.
The command line is your friend.
"Good enough" is the enemy of excellence.
rh <rh_info_store AT YAHOO DOT COM>
Sent by: "ADSM: Dist Stor Manager" <ADSM-L AT VM.MARIST DOT EDU>
03/17/2004 10:49
Please respond to
"ADSM: Dist Stor Manager"
To
ADSM-L AT VM.MARIST DOT EDU
cc
Subject
POSTSCHEDULECMD Timing
Hi ITSM'rs
I'm running backups out of schedules for clients that
have resourceutilization set to >1. I have noticed
that the postschedulecmd runs before all of the
associated sessions that have been started are
finished, ie. before the schedule has completely
finished. Since I use the pre/post to cycle down/up my
applications and database I certainly don't want this
to happen. Has anyone else seen this behavior? I'm
running 5.2.
Thanks,
Rod Hroblak
__________________________________
Do you Yahoo!?
Yahoo! Mail - More reliable, more storage, less spam
http://mail.yahoo.com
|
|
|