ADSM-L

Re: error status in scheduled netware clients

2002-04-08 08:37:07
Subject: Re: error status in scheduled netware clients
From: "Mr. Lindsay Morris" <lmorris AT SERVERGRAPH DOT COM>
Date: Mon, 8 Apr 2002 08:37:09 -0400
You could look at each filespace (query filespace) and see when its last
successful backup date is.

"query events" may hve problems both as you describe - event says error when
client really completed - and also the opposite - event says completed but
nothing happened.  The latter may happen if the client event action was
"command", not "inc" - the command did indeed get kicked off, so the
scheduler reports a success - but then the command fails and the scheduler
doesn'te tell you that.

You also may want to think about how many missed files are allowed, before
an incremental backup is marked failed.  A few are allowed. (Does anybody
have the formula?)

---------------------------------
Mr. Lindsay Morris
Mr. Lindsay Morris
CEO, Servergraph
www.servergraph.com
859-253-8000 ofc
425-988-8478 fax


> -----Original Message-----
> From: ADSM: Dist Stor Manager [mailto:ADSM-L AT VM.MARIST DOT EDU]On Behalf Of
> Tim Brown
> Sent: Monday, April 08, 2002 7:45 AM
> To: ADSM-L AT VM.MARIST DOT EDU
> Subject: error status in scheduled netware clients
>
>
> i recently saw a posting relating to nt client scheuled events
> appearing as "errors"
> when the backup did really complete. i am seeing the same
> situation with netware
> clients. the nt resolution was a ptf level. is there anything i
> can do so that these
> netware backup will indicate as completed..
>
>
> Tim Brown
> Systems Specialist
> Information Systems
> Central Hudson Gas & Electric
> tel: 845-486-5643
> fax: 845-586-5921
>
<Prev in Thread] Current Thread [Next in Thread>