I have a problem with running a scheduled incremental on an SGI 6.2
client.
Perhaps someone can give me a hint.
Server Version: Version 3, Release 1, Level 2.1
Client Version: Version 3, Release 1, Level 0.6
The last entries in the schedlog file are
05/03/99 22:00:05 --- SCHEDULEREC QUERY BEGIN
05/03/99 22:00:05 --- SCHEDULEREC QUERY END
05/03/99 22:00:05 Next operation scheduled:
05/03/99 22:00:05
-------------------------------------------------------
05/03/99 22:00:05 Schedule Name: DAILY
05/03/99 22:00:05 Schedule Name: DAILY
05/03/99 22:00:05 Action: Incremental
05/03/99 22:00:05 Objects:
05/03/99 22:00:05 Options:
05/03/99 22:00:05 Server Window Start: 22:00:00 on 05/03/99
05/03/99 22:00:05
-------------------------------------------------------
05/03/99 22:00:05
05/03/99 22:00:05
Executing scheduled command now.
05/03/99 22:00:05 --- SCHEDULEREC OBJECT BEGIN DAILY 05/03/99 22:00:00
Since then (2 days ago) nothing has happened.
There are no entries for this client in the server activity log file.
But the files have apparently been backed up, as I can see from the
dsm GUI's restore display.
I add the configuration files:
dsm.sys:
SErvername adsm1
NODename sgi1
COMMmethod TCPip
TCPPort 1500
TCPServeraddress adsm1.rrz.uni-koeln.de
passwordaccess generate
schedmode prompted
schedlogret 7
schedlogname /var/adsm/dsmsched.log
errorlogret 7
inclexcl /usr/adsm/inclexcl
dsm.opt:
* SErvername A server name defined in the dsm.sys file
quiet
inclexcl:
exclude /afs/.../*
exclude /vicep*/.../*
exclude /var/cache/.../*
exclude /proc/.../*
exclude /var/tmp/.../*
exclude /scratch/.../*
exclude /.../core
Thanks for any help.
Dietrich
--
Dietrich Koepping
Dietrich Koepping
Rechenzentrum der Universitaet zu Koeln
Berrenrather Str. 136 D50937 Koeln
email: kg AT rrz.Uni-Koeln DOT DE
Tel.: 0221-470-4572 Fax: 0221-470-5881
|
<Prev in Thread] |
Current Thread |
[Next in Thread> |
- Problem with SGI 6.2 client,
Dietrich Koepping <=
|
|
|