Mark,

The scenario is ok, You should do the move and prepare after the
database backup so
that the database backup will also be send offsite with the move drm.

Regards Frans Bijma Solution 6000 B.V. The Netherlands

> -----Original Message-----
> From: Remeta, Mark [mailto:MRemeta AT SELIGMANDATA DOT COM]
> Sent: Monday, April 26, 1999 2:39 PM
> To: ADSM-L AT VM.MARIST DOT EDU
> Subject: Disaster Recovery
>
>
> Hello all,
>
> Can anyone see any problems with the following scenario. I do database
> backups at like 2 in the afternoon. The following day I do
> 4-8 storage pool
> backups. Then I do a 'move drm * wherestate=mountable' followed by a
> 'prepare planprefix=A:' and send the tape's and the floppy
> disk offsite.
> Should I be doing the move drm and prepare statement
> immediately following
> the database backup, will it make a difference?
>
> TIA
>
> Mark Remeta