ADSM-L

Displaying Scheduled Events

1997-01-10 11:40:15
Subject: Displaying Scheduled Events
From: Dave Cannon <dcannon AT VNET.IBM DOT COM>
Date: Fri, 10 Jan 1997 08:40:15 PST
>I have noticed that when I display the scheduled events for a certain
>start and end date, I don't see an event that has been rescheduled.  Is
>this the way it is supposed to work?
>It seems a bit odd because I would have thought that if you rescheduled
>an event that had Failed, you would want to see the original Failed
>event as well as the Completed one.

Query Event shows only the latest status for each event.  If a scheduled
operation is executed successfully, the status will indicate that the
event was successful, although previous attempts at this event may have
been unsuccessful.

Dave Cannon