When I checked the status of the scheduled backup of my node
overnight, I found the following messages:
Querying server for next scheduled event.
Next operation scheduled:
------------------------------------------------------------
Schedule Name: ALW_SCHED
Schedule Name: ALW_SCHED
Action: Incremental
Objects:
Options:
Server Window Start: 00:25:00 on 02/08/1995
------------------------------------------------------------
Command will be executed in 11 minutes.
Command will be executed in 11 minutes.
Executing scheduled command now.
Session established with server ADSMT: MVS
Server Version 1, Release 1, Level 0.10
Server date/time: 02/08/1995 00:40:58 Last access: 02/08/1995 00:34:58
ANS4834E Unable to start scheduled event 'ALW_SCHED'
ANS4835E Either the window has elapsed or the schedule has been deleted
Nonetheless, query event on the server gave the following:
02/08/1995 00:25:00 02/08/1995 00:34:20 ALW_SCHED USASSUN2.DCR- Completed
T.NIH.GOV
So, according to the node, the backup was not carried out, but
according to the server, it was. Can anyone throw any light
on these descrepant messages? Thanks.
------------------------------------------------------------------
Robert P. Klein KL2 AT CU.NIH DOT GOV
Robert P. Klein KL2 AT CU.NIH DOT GOV
Phone: 301-496-7400 Fax: 301-496-6905
Mail: DCRT/CFB/ETS, 12A/1033, 12 SOUTH DR MSC 5607,
BETHESDA, MD 20892-5607
------------------------------------------------------------------
=========================================================================
|